Hello everyone,
I was trying to understand Kopran’s installed and potential upcoming API capacities.
- Mahad – 474 MTPA API (expanding to 924MTPA as per Aug 2020 EC application)
- Panoli (2019 acquired) with 60MTPA capacities (expanding to 1212 MTPA – API + intermediates) as per 2020 EC application.
- Abhinandan Rasayan – 828 MTPA (ref @Pranshinv post above)
So effectively existing API capacities could increase from about 534 MTPA to approx 2500 MTPA over the next 3-5 years.
Also, the Kopran presentations keep referring to Expansions being commissioned and in process of being commissioned – I am presuming that this is within their sanctioned 474 MTPA and not beyond since EC clearance perhaps was pending as late as Aug / Sep 2022.
Is this understanding correct?
Disc – invested.
Thanks and Regards,
1 Mahad Expansion Pre Fea report.pdf (362.7 KB)
2 Panoli Expansion.pdf (209.6 KB)