In the past few years, company has really ramped up their capex spends. I have summarized their finished and announced capexes over time.
Capex
- FY18: Doing 70 cr. capex for a new surfactant plant in Naidupet (30’000 MTPA capacity; delayed and commercialized in FY21)
- FY21: Greenfield capex of 67 cr. (revised cost: 76 cr.) for premium grade pigments at Naidupet (1’500 MTPA capacity; commercialized in FY22)
-
FY22:
– Capex of 21 cr. for specialty chemicals i.e. ingredients for food, cosmetics, personal care (capacity: 1’800 MT) (commercialized in FY23)
– Capex of 24.4 cr. for mixed metal oxides in Naidupet (expected commercialization in FY23)
– Capex for 61.5 cr. for additional pigment capacity in Naidupet (1’500 MTPA) -
FY23
– Capex of 80 cr. in another new Pigments Projects at Naidupeta (capacity: 2250 MT). Expect some portion of the capacity to come online in FY24
– Another project for complex inorganic pigments. Partially completed, balance in FY24. Total cost: 37 cr.