Some of Key insights of Q2 FY24
- Nikhil: Understood. Got it. And the second question I had was then on the Vizhinjam port. Good to see progress on the port, but it would be helpful if we could get clarity on when does scalable commercial operations start at that port?
Karan Adani: So we expect all the equipments to be at port by March of 2024. As you know, it’s a semi automated terminal. It will take us 3 to 4 months to get all the cranes and equipment commissioned. So we would look at basically second half of FY ’25 to commission – to start full-fledged operation.