Unfortunately, SJVN’s execution pace is not building confidence in their aim of 20x capacity till 2030.
7-8 months back I had posted about their planned project completion timelines. As per April’ 2024, they were to go live with a working capacity of 5762 MW and unfortunately, they have achieved only 2466.5 MW installed capacity.
They have been able to achieve only 20-30% of their planned capacity in last 3 years. It seems they have not done any concall in last 5 months to explain what are the challenges and what are the new timelines? Earlier they had been doing concalls every 2-3 months.
See my January post here – SJVN Ltd – Hydroelectric power – #48 by ankiur.jain83