Suzlon Q1 call is a good read. Company expects pan India installations of 5 GW in FY 25.
Also elaborates execution issues:
-
Availability of Land (particularly in Karnataka conversion from agri to non agri is cumbersome).
-
Connectivity issues (delay in substations coming up)
-
Third party BOP capacity build up still happening. Sanghvi should benefit here if they develop a reputation for good service and timely execution. There is a shortage of supply of reliable contractors here.