Since there is a lot riding on the Uplands project, I decided to call the project marketing/sales department to get some information in addition to what is already available on their site.
- Out of land area of 135 acre, the FSI is only 0.25, that is
construction will be only on 25% of the area, leaving 75% as open
spaces. - Environmental clearance has been obtained. No other
approvals are pending. Construction of the villas will start this
month - The Golf course is ready. Landscaping is ready
- Power and water connections are available.
- All permissions related to the land are available. The land is owned by another party (independent, not Arvind Ltd) which has 25% stake in the project, with 75% being with Arvind Infra. Arvind Infra is responsible for construction, sales and marketing. While master plan has been approved by the civic authorities , approval is awaited for some amendment that they made later.
- Total project is for construction of 800 villas, with 1st phase being 280 villas, whose construction will begin shortly. Possession will be within 36-42 months. The 2nd phase will be
launched later (timeline not decided yet). The entire project will be completed by 2020. - No debt is being taken by Arvind Infra (I am not sure how much to rely on this as the info came from the marketing department)
- 4, 5 and 6 bhk villas are available (no apartments). Plot area and construction area options are as follows (see attached file also)
o 4bhk
(1) plot area 640 sq yard / construction area 325 sq yard – total cost Rs. 1.56 cr (excluding government costs such as stamp duty, registration etc., but including maintenance, club house etc charges)
(2) 850/430 – 2.06 crores
(3) 1128/430 – 2.4 crores
o 5bhk – 1500/550 – 3.13 cr
o 6bhk – plot area 2000-2700 sq. yard and construction area 675 sq. yard. Starting from 4.5 crores.
- No cash payment – all white (I checked this specifically). In all their projects it seems.
Rough back of the envelop calculations:
o Average constructed area per villa is appx. 616 sq yard which is 5544 sq ft.
o Average cost per sq. ft. works out to 4200 Rs.
o Average villa cost is Rs 2.25 cr. For 800 villas it is 1800 crores. 75% of which works out to 1350cr. Sort of gells with management presentation which gives their share of revenue as Rs 1200 cr.
This all sounds very posh and upmarket, however chats with a few friends in Ahmedabad indicate that such aspirational projects have a fair bit of demand in that area. If some board members are from Ahd, then their views are solicited.
Cant attach their presentation and floor plans as the file sizes exceed permitted limit.